TerraPower, the nuclear technology company founded by Bill Gates, has marked with a ceremony the start of construction for its demonstration Natrium advanced nuclear plant complex near a retiring coal plant at Kemmerer, Wyoming.

A spokesperson for TerraPower told NucNet that the inaugural dig, attended by Gates, who is also company chairman, chief executive Chris Levesque and Wyoming governor Mark Gordon, was for the non-nuclear part of the plant, the first part of which will be a sodium test and fill facility.

The Natrium demonstration plant includes three separate project parts: a sodium test and fill facility, a fuel fabrication facility, and the reactor itself. The test and fill facility and the reactor itself will be built in Kemmerer, while the fuel fabrication facility is planned for Wilmington, North Carolina, near existing fuel fabrication facilities of TerraPower’s Natrium design partner, GE Hitachi.

The test and fill facility is a standalone, non-nuclear building that will be next to the site of the Natrium plant and will operate independently. It will provide a testing site for the reactor’s sodium coolant system by receiving, sampling, processing, and storing liquid sodium which will ultimately be delivered to the Natrium reactor.

“Of course, other access roads etc. are required for operation. But the primary focus is on the test and fill structure,” said the spokesperson

The Natrium reactor is a 345-MW electric sodium-cooled fast reactor with a molten salt energy storage system that is being designed to flexibly operate with renewable power generators to help decarbonise the electric grid.

TerraPower applied for a rector construction permit to the US Nuclear Regulatory Commission (NRC) in April 2024. Last month the NRC said it had accepted the application giving formal start of the licensing process.

Levesque has said that TerraPower is aiming to start nuclear-related works in 2026 subject to receiving a permit from the NRC. The plant is expected to be completed by 2029-2030.

US-based Bechtel has been selected for the construction of the plant and its infrastructure.

The Natrium demonstrator is co-funded by the US Department of Energy under its Advanced Reactor Demonstration Program (ARDP) programme.

The DOE has a seven-year, $2bn (€1.86bn) agreement to fund the project, while TerraPower is matching this investment dollar-for-dollar for a total cost estimated at about $4bn.